Planning

Project Schedule — Gantt

Uncompleted BOQ items in construction order across 60 days. Drag bars to reschedule, add or remove lines, and edit the timeline headers.

Overall progress61%
End 2027-01-20
Task
Day
22
23
24
25
26
27
28
29
30
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

7. Wall & Ceiling Finishes

Finishes · 33d10 Oct

33d · 58%

8. Floor Finishes

Marble · 28d10 Oct

28d · 45%

9. Wall Tiling

Marble · 21d25 Oct

21d · 45%

10. Ceilings

Finishes · 48d10 Oct

48d · 58%

12. Windows & Glazing

Windows · 39d22 Oct

39d · 13%

15. Bathrooms & Sanitary

Bathrooms · 9d30 Nov

9d · 0%

16. Plumbing & Drainage

MEP · 60d10 Oct

60d · 42%

18. Electrical Power

MEP · 31d10 Oct

31d · 42%

19. Lighting

MEP · 31d31 Oct

31d · 42%

External tiling

Civil · 14d10 Oct

14d · 98%

23. Pool Works — If Applicable

Landscaping · 36d03 Nov

36d · 43%

26. Testing, Commissioning & Handover

Base Scope · 10d29 Nov

10d · 82%