Progress Sheet

Mohammed Albaker Villa

Project Completion
61.3%

1

Villa

61.3%

Overall Completion

Completion: 61.3%

ItemDescriptionQuantity% DoneActions
1. Preliminaries & General Requirements
94%
1.1

Mobilisation and demobilisation

N/A
—
85%
1.2

Site establishment and temporary facilities

N/A
—
100%
1.4

Temporary electricity and water

N/A
—
90%
1.5

Scaffolding and access equipment

N/A
—
100%
2. Survey, Setting Out & Existing Conditions
100%
2.5

Testing of existing services

N/A
—
100%
2.6

Protection of existing finishes/services

N/A
—
100%
3. Demolition & Removal Works
100%
3.1

Demolition of existing walls

N/A
—
100%
3.2

Removal of partitions

N/A
—
100%
3.15

Core cutting and openings

N/A
—
100%
3.17

Making good after demolition

N/A
—
100%
4. Civil & Blockwork
100%
4.1

New block walls

N/A
—
100%
4.2

Partition walls

N/A
—
100%
4.3

Cement blockwork

N/A
—
95%
4.4

Lightweight/block partitions

N/A
—
100%
4.5

Door openings

N/A
—
100%
4.6

Lintels

N/A
—
100%
4.7

Concrete works

N/A
—
100%
4.8

Structural alterations

N/A
—
100%
4.10

Plastering

N/A
—
100%
4.14

Waterproofing preparation

N/A
—
100%
5. Floor Preparation
100%
5.4

New cement screed

N/A
—
100%
5.10

Floor chipping for MEP conduits

N/A
—
100%
6. Waterproofing
91%
6.1

Bathroom waterproofing

N/A
—
100%
6.4

Balcony waterproofing

N/A
—
90%
6.5

Roof waterproofing

N/A
—
82%
6.6

Terrace waterproofing

N/A
—
92%
7. Wall & Ceiling Finishes
70%
7.1

Internal plastering

N/A
—
100%
7.12

Stucco finish

N/A
—
100%
7.13

Paint preparation

N/A
—
100%
7.14

Primer

N/A
—
100%
7.15

Internal wall paint

N/A
—
0%
7.16

Ceiling paint

N/A
—
43%
7.18

External paint where applicable

N/A
—
48%
8. Floor Finishes
42%
8.1

Porcelain tiles

N/A
—
82%
8.3

Marble

N/A
—
85%
8.4

Granite

N/A
Pending client material
—
100%
8.14

Skirting

N/A
—
0%
8.18

Grouting

N/A
—
0%
9. Wall Tiling
50%
9.1

Bathroom wall tiles

N/A
—
100%
9.2

Kitchen wall tiles

N/A
Pending client material
—
34%
9.6

Tile grout

N/A
—
0%
10. Ceilings
37%
10.1

Gypsum board ceilings

N/A
—
50%
10.11

Ceiling access panels

N/A
—
52%
10.12

Shadow gaps

N/A
—
45%
10.13

Inspection hatches

N/A
—
0%
11. Doors & Ironmongery
0%
11.1

Main entrance doors

N/A
Variation / supplier change
—
0%
11.2

Internal timber doors

N/A
Variation / supplier change
—
0%
12. Windows & Glazing
13%
12.2

uPVC windows

N/A
—
13%
14. Kitchen
83%
14.7

Drainage connections

N/A
—
83%
15. Bathrooms & Sanitary
0%
15.1

WC

N/A
Pending client material
—
0%
15.2

Wash basin

N/A
Pending client material
—
0%
15.3

Vanity

N/A
Pending client material
—
0%
15.4

Bidet

N/A
Pending client material
—
0%
15.5

Shower mixer

N/A
Pending client material
—
0%
15.6

Shower set

N/A
Pending client material
—
0%
15.9

Bathroom mirrors

N/A
Pending client material
—
0%
15.11

Floor drains

N/A
Pending client material
—
0%
16. Plumbing & Drainage
53%
16.1

Cold-water pipework

N/A
—
77%
16.2

Hot-water pipework

N/A
—
76%
16.3

Drainage pipework

N/A
—
83%
16.4

Soil and waste pipes

N/A
—
84%
16.5

Vent pipes

N/A
—
87%
16.6

Water tanks

N/A
—
40%
16.7

Pumps

N/A
—
47%
16.8

Water heaters

N/A
—
40%
16.15

Pressure testing

N/A
—
0%
16.16

Drainage testing

N/A
—
0%
18. Electrical Power
28%
18.1

Main DB

N/A
—
0%
18.2

Sub-DBs

N/A
—
0%
18.3

Distribution boards

N/A
—
0%
18.4

MCCB/MCB/RCD

N/A
—
0%
18.8

Conduits

N/A
—
76%
18.9

Electrical cables

N/A
—
69%
18.10

Junction boxes

N/A
—
66%
18.11

Isolators

N/A
—
40%
18.12

Switches

N/A
Pending client material
—
0%
18.13

Socket outlets

N/A
Pending client material
—
0%
18.23

Testing and commissioning

N/A
—
0%
19. Lighting
0%
19.1

Downlights

N/A
Pending client material
—
0%
19.10

Cove lighting

N/A
Pending client material
—
0%
19.11

Outdoor lighting

N/A
Pending client material
—
0%
19.18

Timers

N/A
—
0%
20. ELV / Low Voltage Systems
47%
20.1

Data cabling

N/A
—
67%
20.2

Telephone points

N/A
—
69%
20.3

Wi-Fi access points

N/A
—
86%
20.4

TV points

N/A
—
0%
20.6

CCTV

N/A
—
60%
20.19

Smart-home controls

N/A
—
0%
22. External Works
50%
22.4

Driveway works

N/A
—
0%
22.17

Drainage

N/A
—
81%
22.19

Garden electrical points

N/A
—
70%
23. Pool Works — If Applicable
40%
23.1

Pool civil works

N/A
—
52%
23.2

Pool waterproofing

N/A
—
75%
23.3

Pool tiles

N/A
—
0%
23.5

Pool drainage

N/A
—
73%
23.6

Pool filtration

N/A
—
0%
23.11

Pool deck

N/A
—
0%
23.12

Outdoor shower

N/A
—
80%
25. External / Villa Services
56%
25.7

EV charger provision

N/A
—
56%
26. Testing, Commissioning & Handover
0%
26.21

Authority approvals

N/A
—
0%

On hold — not counted in progress

17 items excluded from the overall completion percentage.

Pending Client Materials

15

Waiting on the client to supply — left out of the overall completion.

  • 8.4Granite
  • 9.2Kitchen wall tiles
  • 15.1WC
  • 15.2Wash basin
  • 15.3Vanity
  • 15.4Bidet
  • 15.5Shower mixer
  • 15.6Shower set
  • 15.9Bathroom mirrors
  • 15.11Floor drains
  • 18.12Switches
  • 18.13Socket outlets
  • 19.1Downlights
  • 19.10Cove lighting
  • 19.11Outdoor lighting

Variation / Supplier Change Decisions

2

Open decision — left out of the overall completion.

  • 11.1Main entrance doors
  • 11.2Internal timber doors

Notes of the Day

Submittals

0 total

No submittals uploaded yet.

Daily Progress Photos

No photos for today yet. Add today's site photos above.

Earlier days · PDF only

254 photos
  • 04 Nov 20264 photos
  • 01 Nov 20263 photos
  • 27 Oct 202619 photos
  • 25 Oct 202628 photos
  • 21 Oct 202617 photos
  • 19 Oct 202649 photos
  • 15 Oct 202642 photos
  • 13 Oct 202624 photos
  • 11 Oct 202646 photos
  • 07 Oct 202622 photos

Villa Maitha Dhahir S K Al Muraikhi

Bill of Quantities · Progress Tracker · Rev 6 · 26/3/2026 · Prepared for Maitha Dhahir S K Al Muraikhi