Pending from Client
15 items awaiting the client- 8.4
Granite
8. Floor FinishesN/A - 9.2
Kitchen wall tiles
9. Wall TilingN/A - 15.1
WC
15. Bathrooms & SanitaryN/A - 15.2
Wash basin
15. Bathrooms & SanitaryN/A - 15.3
Vanity
15. Bathrooms & SanitaryN/A - 15.4
Bidet
15. Bathrooms & SanitaryN/A - 15.5
Shower mixer
15. Bathrooms & SanitaryN/A - 15.6
Shower set
15. Bathrooms & SanitaryN/A - 15.9
Bathroom mirrors
15. Bathrooms & SanitaryN/A - 15.11
Floor drains
15. Bathrooms & SanitaryN/A - 18.12
Switches
18. Electrical PowerN/A - 18.13
Socket outlets
18. Electrical PowerN/A - 19.1
Downlights
19. LightingN/A - 19.10
Cove lighting
19. LightingN/A - 19.11
Outdoor lighting
19. LightingN/A
BOQ items pending client materials
15 pending client materials · 2 variations · left out of project completion- 1.1
Mobilisation and demobilisation
- 1.2
Site establishment and temporary facilities
- 1.4
Temporary electricity and water
- 1.5
Scaffolding and access equipment
- 2.5
Testing of existing services
- 2.6
Protection of existing finishes/services
- 3.1
Demolition of existing walls
- 3.2
Removal of partitions
- 3.15
Core cutting and openings
- 3.17
Making good after demolition
- 4.1
New block walls
- 4.2
Partition walls
- 4.3
Cement blockwork
- 4.4
Lightweight/block partitions
- 4.5
Door openings
- 4.6
Lintels
- 4.7
Concrete works
- 4.8
Structural alterations
- 4.10
Plastering
- 4.14
Waterproofing preparation
- 5.4
New cement screed
- 5.10
Floor chipping for MEP conduits
- 6.1
Bathroom waterproofing
- 6.4
Balcony waterproofing
- 6.5
Roof waterproofing
- 6.6
Terrace waterproofing
- 7.1
Internal plastering
- 7.12
Stucco finish
- 7.13
Paint preparation
- 7.14
Primer
- 7.15
Internal wall paint
- 7.16
Ceiling paint
- 7.18
External paint where applicable
- 8.1
Porcelain tiles
- 8.3
Marble
- 8.4
Granite
- 8.14
Skirting
- 8.18
Grouting
- 9.1
Bathroom wall tiles
- 9.2
Kitchen wall tiles
- 9.6
Tile grout
- 10.1
Gypsum board ceilings
- 10.11
Ceiling access panels
- 10.12
Shadow gaps
- 10.13
Inspection hatches
- 11.1
Main entrance doors
- 11.2
Internal timber doors
- 12.2
uPVC windows
- 14.7
Drainage connections
- 15.1
WC
- 15.2
Wash basin
- 15.3
Vanity
- 15.4
Bidet
- 15.5
Shower mixer
- 15.6
Shower set
- 15.9
Bathroom mirrors
- 15.11
Floor drains
- 16.1
Cold-water pipework
- 16.2
Hot-water pipework
- 16.3
Drainage pipework
- 16.4
Soil and waste pipes
- 16.5
Vent pipes
- 16.6
Water tanks
- 16.7
Pumps
- 16.8
Water heaters
- 16.15
Pressure testing
- 16.16
Drainage testing
- 18.1
Main DB
- 18.2
Sub-DBs
- 18.3
Distribution boards
- 18.4
MCCB/MCB/RCD
- 18.8
Conduits
- 18.9
Electrical cables
- 18.10
Junction boxes
- 18.11
Isolators
- 18.12
Switches
- 18.13
Socket outlets
- 18.23
Testing and commissioning
- 19.1
Downlights
- 19.10
Cove lighting
- 19.11
Outdoor lighting
- 19.18
Timers
- 20.1
Data cabling
- 20.2
Telephone points
- 20.3
Wi-Fi access points
- 20.4
TV points
- 20.6
CCTV
- 20.19
Smart-home controls
- 22.4
Driveway works
- 22.17
Drainage
- 22.19
Garden electrical points
- 23.1
Pool civil works
- 23.2
Pool waterproofing
- 23.3
Pool tiles
- 23.5
Pool drainage
- 23.6
Pool filtration
- 23.11
Pool deck
- 23.12
Outdoor shower
- 25.7
EV charger provision
- 26.21
Authority approvals
Mohammed Albaker Villa
Client-Supplied Materials
No materials scheduled yet.